Shanahan Engineering completed the Hydrotest of all 12 systems on Unit 11 HRSG in 7.5 days at the Langage Energy Center. "Through detailed preplanning and preparation, our test crew were able to complete the works ahead of the planned duration", said Tim Noone, Shanahan Engineering Project Controls Manager. Shanahan Engineering is the erection contractor for two once through HRSG units for Alstom Power.